Work Continues with Construction of West Abutment Stem Wall

The Contractor has completed the entire removal of the existing center pier and construction of the west abutment concrete footing. Work currently continues with forming and tying the reinforcing steel for the west abutment stem wall. Concrete pour for the stem wall is scheduled for Friday, May 20th.  