Work Continues with Concrete Placement for the New Center Pier

Work will started early this morning (August 4th ) at 4 am with the placement of approximately 650 cubic yards of concrete inside the cofferdams for the new center pier. Early morning work is required in order to pour the concrete in cooler temperatures as the forecasted temperatures in the middle of the day are in the upper 80s. We apologize for this inconvenience to the local residents and will do everything we can to minimize this type of inconvenience in future work.