Tag Archives: Construction

Western Avenue Approach Paving

Installation of Bituminous Pavement Complete

Both roadway approaches to the bridge are now paved and guardrail has been installed. Work will continue into the next few weeks with the installation of gravel shoulders, sidewalk hand rail, traffic and street signs, line stripping and general site cleanup. Bridge is currently anticipated to be opened to traffic on August 5th.

Paving Operations at the Western Avenue Bridge

Work Continues with Concrete Deck Placement

Reinforcing steel for the deck has been installed. The crew is getting ready to pour the concrete for the deck of the eastern span on Wednesday, April 19th. A portion of Western Avenue, between Patterson Hill Road and Cote Hill Road, will be closed during the concrete pour from 8:00 am – 3:00 pm.  During the closure a detour will be in place with the aid of flaggers. We apologize for this inconvenience to the local residents and will do everything we can to minimize this type of inconvenience in future work.